NEWS FROM LODJA - THE CONGO

The supplies have arrived!

The supplies and material, not to mention Paul's truck have safely arrived in Lodja. Finally.

As I mentioned in my last blog, in the meantime, Paul has been keeping the workers busy with a road project and bridge construction in preparation for the Annual Conference.


Here are before and after pictures of the Loyehi bridge project. This is
a bridge Paul and his workers
rebuilt and is an excellent example of the quality of work we can
expect with the dam construction.


What else have they been doing? In order to get a higher quality of soil for the dam, it was necessary to build a gravel road on the other side of the dam. That road is now complete!

The soil with a heavier clay content is on the other side, Paul has a dump truck on the way to haul it and before too much longer, the dam will be going up. Rock-n-roll!

The project is a little behind the original schedule but still within budget. Paul will send some pictures and another update soon.